- Executed below stated works related to transportation and installation of jacket in Karabakh oilfield located in Caspian Sea for the whole period of transportation and installation of jacket
- - Respond to all inquiries of state authorites directed by Company, carry out all related correspondence with state authorities, and keeps Company informed about the result of such correspondence
Adaptation of Absheron EPS platform
Performed Year: 2019

Engineering Design of 3 CNG (Compressed Natural Gas) stations
Performed Year: 2019
WREP Casing Removal
Performed Year: 2019-2020

Executed below stated works related to transportation and installation of jacket in Karabakh oilfield
Performed Year: 2020

Preparation of the project regarding new oil wells
Performed Year: 2017-2019
· Preparation environmental impact assessment

Design of Oil Pipeline – 2.6 km, D-530 mm
Performed Year: 2020
Obtaining relevant license from relevant department of Ministry of Agriculture of the Republic of Azerbaijan
Performed Year: 2017