Adaptation of Absheron EPS Platform

Performed Year: 2019
Customer: JOCAP (SOCAR Absheron (50%) and TOTAL E&P Absheron B. V. (50%))
arrow

Adaptation of Absheron EPS platform (topside, jacket, link to existing system via bridge), 34 km of 12” fully rated (500 bar) insulated multiphase flow line, 34 Umbilical for controls, chemical and communication. 
·         Design of  lightning protection 
·         Design  HVAC systems 
·         Safety Declarations 
·         Construction Plan 
·         Project passports 

project

Engineering Design of 3 CNG (Compressed Natural Gas) stations

Performed Year: 2019
Customer: Azpetrol LTD LLC
arrow
project

WREP Casing Removal

Performed Year: 2019-2020
Customer: Körpü Bina Tikinti MMC
arrow

 
The contract is about “New highway construction under “Azeravtoyol” State Agency in Ujar district crossing with BTC, SCPX, SCP and WREP export pipelines as a part of  (R32) Ujar-Zardab-Aghjabadi highway reconstruction project” is awarded between 2019-2020 years for the below  services which were implemented by “EXPERİMENT” Scientific Production Center 

·         Management of the Project.  
·         Preparing engineering drawings crossover section with the new road and BTC, SCP, SCPX, WREP pipeline. 
·            Preparing engineering drawings for casing removal at WREP 
·          Preparation of all necessary documents related to obtaining a work permit from BP (method of statement, etc.) 
·            Excavation, backfilling and fencing of the area,  laying of concrete slabs are in full compliance with BP requirements 

project

Executed Below Stated Works Related to Transportation and Installation of Jacket in Karabakh Oilfield

Performed Year: 2020
Customer: Karabakh Operating Company in Azerbaijan Republic
arrow

  •  Executed below stated works related to transportation and installation of jacket in Karabakh oilfield located in Caspian Sea for the whole period of transportation and installation of jacket

-  To obtain all licences, permits required by state authorities on behalf of Company and presents to company 
  • -  Respond to all inquiries of state authorites directed by Company, carry out all related correspondence with state authorities, and keeps Company informed about the result of such correspondence

project

Preparation of the Project Regarding New Oil Wells

Performed Year: 2017-2020
Customer: Binagadi Oil Operating Company
arrow

 
·         Preparation of the project regarding  new oil wells (85 new wells) 

·         Preparation environmental impact assessment 

project

Design of Oil Pipeline – 2.6 km, D-530 mm

Performed Year: 2020
Customer: Absheron Logistic Center
arrow
project

Audit Gas Supply System for Norm Cement

Performed Year: 2019-2020
Customer: Norm ASC
arrow
project